Case Studies

BAE Systems Case Study

General Description

  • Industrial Engineering Support
  • Analyze current state and implement cost savings based on future state plan
  • Develop, train and implement Production System
baes

Scope

  • Developed Lean Training Program (included all salaried and hourly personnel)
  • Developed manpower reduction plan and reduced hourly direct labor from 232 heads to 95 equaling $4.8 million in savings
  • Went from 4 shifts to 2 shifts at 4 days/10 hours
  • Developed new layout and material flow plans and reduced internalWIP by $5 million
  • Launched new automated paint system

Success

Savings for the customer totaling over $5,000,000

Contact Us to Learn More About What TPT Can Do For You!

TPT is the leading provider of facility planning, staffing solutions and engineering services. Contact us to speak with one of our specialists today!