BAE Systems Case Study
Scope
- Developed Lean Training Program (included all salaried and hourly personnel)
- Developed manpower reduction plan and reduced hourly direct labor from 232 heads to 95 equaling $4.8 million in savings
- Went from 4 shifts to 2 shifts at 4 days/10 hours
- Developed new layout and material flow plans and reduced internalWIP by $5 million
- Launched new automated paint system
Success
- Savings for the customer totaling over $5,000,000
Contact Us to Learn More About What TPT Can Do For You!
TPT is the leading provider of facility planning, staffing solutions and engineering services. Contact us to speak with one of our specialists today!